Production Order Stages

Tip of the Day: In Microsoft D365 Finance and Supply Chain (D365 F&SC), in Production Control, when a Production Order or Batch Order is processed, it goes through multiple stages. To learn more, see the guide below.


To advance your consulting skills, let me share my Microsoft Dynamics D365 F&SC expertise with you by signing for my post notifications at www.intraclouddynamics.com or www.aliciakeener.com or subscribe to my YouTube Channel @aliciakeener6544 MVP Contributor ID = ?wt.mc_id=MVP_346423

 

 



When a Production Order or Batch Order is processed, it goes through multiple stages.



 

Created

·       You can create a production order, batch order, or kanban manually, or you can configure the system to generate them based on various demand signals.

·       Master planning creates production orders, batch orders, or kanbans by firming planned orders.

·       Other demand signals are sales orders or pegged supply signals from other production orders or kanbans.

·       For fixed quantity kanbans, demand signals are generated when kanbans are registered as empty.

 

Estimated

·       You can calculate estimates for material and resource consumption.

·       The estimation generates inventory transactions for raw materials that have a status of On order.

·       The receipts for main products, co-products, and by-products are generated when production orders or batch orders are estimated.

·       If the BOM contains lines of the Pegged supply type, purchase orders for materials or subcontracted operation services are generated and pegged to the production order or batch order.

·       Items or orders are reserved according to the reservation strategy of the production order, and the price of the finished goods is calculated based on parameter settings.

 

Scheduled

·       You can schedule production based on operations, individual jobs, or both.

 

Operations scheduling

·       This scheduling method provides a rough, long-term plan.

·       By using this method, you can assign start and end dates to production orders. If the production orders are attached to route operations, you can assign them to cost center groups.

 

Job scheduling

·       This scheduling method provides a detailed plan.

·       Each operation is broken down into individual jobs that have specific dates, times, and assigned operations resources.

·       If finite capacity is used, jobs are assigned to operations resources based on availability.

·       You can view and change the schedule in a Gantt chart.

 

Kanban schedule

·       Kanban jobs are scheduled on the kanban schedule board or automatically scheduled based on the automatic planning configuration of the kanban rules.

 

Released

·       You can release the production order or batch order when the schedule is finished, and the material is available to be picked or prepared.

·       The material availability check helps the shop floor supervisor assess the availability of material for the production orders or batch orders.

·       You can also print the production order documents, such as the pick lists, job card, route card, and route job.

·       When the production order is released, the status of the order changes to indicate that production can begin.

·       When warehouse management is used, release of the production order or batch order releases the production BOM lines to warehouse management. Warehouse waves and warehouse work are then generated according to the setup of the warehouse.

 

Prepared/Picked

·       When all materials and resources have been staged at the production location, the production BOM lines or kanban lines are updated to a status of Picked.

·       Pegged supply orders and related warehouse work are typically completed at this stage.

·       The kanban cards or job cards that are required to report production progress should be assigned and printed.

 

Started

·       When a production order, batch order, or kanban is started, you can report material and resource consumption against the order.

·       The system can be configured to automatically post the material and resource consumption that are allocated to the order when the order is started.

o   This allocation is known as pre-flushing, forward flushing, or auto consumption.

o   You can manually allocate materials to production orders or batch orders by creating additional picking list journals. You can also manually allocate labor and other route costs to the order.

o   If you're using operations scheduling, you can allocate these costs by creating a route card journal.

o   If you're using job scheduling, you can allocate the costs by creating a job card journal.

o   Production orders or batch orders can be started in batches of the requested final quantity.

o   Within a production order, batch order, or kanban, the jobs that are created can be started and reported separately through journals, the manufacturing execution terminal (MES Terminal), or the kanban boards.

• Report progress/Complete jobs

·       Use the MES Terminal, production journals, kanban boards, or mobile scanning capabilities to report the production progress by job or resource.

·       Material and resource consumption will be posted, and the status of the related kanbans, production orders, and batch orders might be updated to Received or Reported as finished.

·       Put-away work for the warehouse might be created, depending on the warehouse configuration.

 

Reported as finished (the product receipt)

·       When a production order or batch order is reported as finished, the quantity of the finished goods that were completed is updated in inventory.

·       This quantity includes the quantity of relevant co-products and by-products.

·       If you're using work-in-process (WIP) accounting, a ledger journal is generated to reduce the WIP accounts and increase the inventory of the finished goods.

·       When the cost of a production order is calculated, the actual cost of the production is posted. If the material and labor costs that are associated with a production aren't already allocated in a journal or by pre-flushing, they can be automatically allocated through back-flushing.

·       Allocation through back-flushing involves the post-deducting of inventory transaction processes.

·       If the production order is completed, select the End job check box to change the remaining status to Ended. Otherwise, leave the field empty to enable reporting of additional quantities that are produced.

 

Quality assessment

·       A product receipt can trigger the creation of quality orders, depending on the configuration of test processes and the quality rules that are established for specific products.

·       Because a quality order can update the inventory status or the batch attributes of the tested products, quality assessment is a mandatory process in many industries.

 

Put away and Ship to order

·       After product receipt and quality assessment, optional put-away work directs the received products to the next point of consumption, to a finished goods warehouse, or to a shipment zone if there are ship-to-order requirements.

 

Ended

·       Before production is ended, actual costs are calculated for the quantity that was produced.

·       All estimated costs of material, labor, and overhead are reversed and replaced with actual costs.

·       If you select the End job check box when you run the cost calculation, the production order status changes to Ended.

·       This status prevents any additional costs from being posted to a completed production order.